How Much Does Dredging Cost? Per Cubic Yard and Per Acre

Dredging costs $5.90 to $60 per cubic yard depending entirely on what kind of dredging you mean. A 2026 federal award at Toledo Harbor works out at $7.07 per cubic yard, and large harbour maintenance generally runs $5.90 to $7.12. Marsh creation is $7.33 to $8.21. Beach renourishment came in at $26.17 to $36.00 on two 2026 awards, above the 1970 to 2020 average of $14 to $18 in 2023 dollars. Small pond and lake work is $20 to $60 per cubic yard, though that figure comes from consumer cost guides rather than contract data. Contaminated sediment is a different world: an earlier version of this page put PFAS treatment at $133 to $231 per cubic yard on top, a figure we have no source for.

November 2026 update: federal data show how widely dredging costs vary. A Congressional Research Service analysis of US Army Corps of Engineers contracts found average harbor maintenance dredging costs rose from $1.74 to $5.77 per cubic yard between 1970 and 2018 in inflation-adjusted terms, and that district averages for large contracts in 2014-2018 ranged from $2.62 per cubic yard in New Orleans to $24.27 in San Francisco. Disposal can cost as much again: Rhode Island proposed raising its dredged-material disposal fee from $11.65 to $35 per cubic yard in 2025.
🚧Dredging Cost Tracker
Updated: November 2026
2026 Award-Derived$7.07 to $46.80 /cu yd
Grade / ItemLowHighUnit
Toledo Harbor, 2026 task order (US Army release)$7.07$7.07USD/cu yd
Cleveland Harbor 2026, small vol$46.80$46.80USD/cu yd
Large harbour maintenance$5.90$7.12USD/cu yd
Lake Borgne marsh, completed$7.33$7.33USD/cu yd
Lake Borgne marsh, FY2027 plan$8.21$8.21USD/cu yd
Ocean City MD beach, Sep 2026$26.17$26.17USD/cu yd
Grand Strand beach, Sep 2026$33.49$36.00USD/cu yd
Beach nourishment, 1970-2020 avg$14$18USD/cu yd 2023
Small pond or lake (Angi guide)$20$60USD/cu yd est
Large project mobilisation (illustrative, unsourced)$2,500,000$2,500,000USD
US-built 16 in CSDNo public priceNo public pricen/a
China-built 16-20 in CSD (unsourced)$450,000$650,000USD FOB
Reviewed 23 November 2026. The Toledo Harbor figure is a US Army task order value divided by the published volume (release of 10 August 2026); small pond figures are from the Angi pond dredging cost guide (undated). The other per cubic yard rows come from an earlier review against US Army Corps of Engineers award releases and state plans and were not re-traced; rows marked unsourced have no named source on record. Full heavy equipment cost guide

Dredging cost per cubic yard

Type of work Cost per cubic yard
Toledo Harbor, FY2026 award $7.07
Large harbour maintenance $5.90 to $7.12
Lake Borgne marsh, completed $7.33
Lake Borgne marsh, FY2027 plan $8.21
Ocean City MD beach, Sept 2026 $26.17
Grand Strand beach, Sept 2026 $33.49 to $36.00
Beach nourishment, 1970 to 2020 average $14 to $18 in 2023 dollars
Cleveland Harbor 2026, small volume $46.80
Small pond or lake $20 to $60, see note

The two 2026 awards at the top of that table are the most useful lines, because they are the same category of work in the same year varying by a factor of six. Toledo Harbor moved roughly 750,000 cubic yards for $5.3 million, or $7.07 a yard. Cleveland Harbor moved roughly 250,000 for $11.7 million, or $46.80 a yard, a gap the awards themselves do not explain (see our analysis below). Anyone who quotes you a single national dredging price is not describing your job.

Two things worth knowing about the official data

First, there is no published FY2026 national average. The newest official aggregate dataset covers 1963 to 2023 and is not publicly retrievable; the redeveloped public interface returns an application error. Every per-yard figure above that is marked as award-derived is calculated by dividing a published contract value by a published volume, so you can re-check the arithmetic yourself.

Second, the small pond figures are weaker than the rest of this page. They come from consumer cost-guide sites rather than contract awards, and no contract-level source could be found for them or for the PFAS treatment adder that an earlier version of this page quoted at $133 to $231 per cubic yard. Both are flagged rather than deleted, because they are the only figures available at that scale, but treat them as indicative.

Why volume changes the price so much

Dredging has an enormous fixed cost and a modest variable cost. As an illustration, take $2.5 million to mobilise a large dredge on a major project (we have no named source for that figure). That cost is the same whether you remove 100,000 cubic yards or 2 million.

Spread $2.5 million across 2 million cubic yards and mobilisation adds $1.25 per yard. Spread it across 100,000 yards and it adds $25 per yard. This is the entire reason harbour work costs $6 and your pond costs $40.

It also means that on any project, the single most effective cost lever is doing more of it at once. Two small dredging jobs a year apart cost dramatically more than one job twice the size.

Small pond and lake dredging

Basis Cost
Per cubic yard $20 to $60
Per acre $5,000 to $30,000
Typical total job $2,500 to $40,000

These three ranges match the Angi pond dredging cost guide (undated; read 23 November 2026), which gives $15,000 as the average for most residential ponds and $7,000 to $30,000 as the typical range. For a private pond, the practical variables are access, disposal and method.

Mechanical dredging uses an excavator, either from the bank or on a barge or pontoons, to dig material out. Best when the pond can be drained or partially drained, when the material is firm, and when there is somewhere on the property to place the spoil. Usually the cheapest option on a small site.

Hydraulic dredging pumps a slurry of sediment and water through a pipe to a containment area. Works without draining, causes less disturbance, and handles soft silt well. It needs a place to dewater the slurry, which is often the constraint.

The question that decides your price is not which method but where the material goes. Spoil that can be spread on site is nearly free to dispose of. Spoil that has to be dewatered, loaded and trucked to a landfill can cost more than the dredging.

Contaminated sediment

If the sediment is contaminated, the equipment cost stops being the story. An earlier version of this page put PFAS treatment alone at $133 to $231 per cubic yard, a figure we have no source for; if it is right, it is roughly 19 to 39 times the cost of the dredging itself on a harbour project.

Contamination brings characterisation sampling before the work, a regulated disposal pathway, water treatment for the return flow, monitoring during the work, and a much longer permitting timeline. Heavy metals, PCBs and hydrocarbons all trigger versions of the same escalation.

The practical advice is to sample early. A sediment characterisation costs a few thousand dollars and determines whether your project is a $30,000 job or a $300,000 one. Finding out after mobilisation is the expensive way.

Buying a dredge

Machine Price
US-built 16 inch cutter suction dredge No public price found
China-built 16 to 20 inch cutter suction dredge $450,000 to $650,000

We found no public price for a US-built dredge of this size, so the gap cannot be measured here, and the China-built range has no named source on record. The governing statute is the Foreign Dredge Act of 1906, not the Jones Act, and it requires US-built, US-flagged and US-crewed vessels for dredging in US waters. It was unchanged through 2026. A Jones Act waiver was issued in March 2026 and extended to August, but it covered commodity carriage and did not touch dredging at all (we have not re-checked that waiver for this update). That requirement, plus build standards and labour cost, is most of the difference.

If you are dredging in US waters commercially, the imported dredge may not be legally usable for the work you want it for. Check this before you price anything.

Our analysis: which figures are traced, and what they imply

Figure on this page Source status on 23 November 2026
Toledo Harbor, $7.07 per cubic yard Traced: US Army release dated 10 August 2026 ($5.3 million task order, about 750,000 cubic yards, Ryba Marine Construction).
Small pond or lake: $20 to $60 per cubic yard, $5,000 to $30,000 per acre Traced: Angi pond dredging cost guide (undated; read 23 November 2026).
Federal averages 1970 to 2018 and district range 2014 to 2018 Linked: Congressional Research Service report (see sources).
Cleveland Harbor $46.80; large harbour maintenance $5.90 to $7.12; Lake Borgne $7.33 and $8.21; Ocean City $26.17; Grand Strand $33.49 to $36.00; beach average $14 to $18 From an earlier review against Corps award releases and state plans. No link was recorded and we did not re-trace them in this update.
Mobilisation $2.5 million; China-built dredge $450,000 to $650,000; PFAS treatment $133 to $231 per cubic yard No named source on record. Illustrative only.

What the Toledo release adds. The $5.3 million is the first task order of a two-year contract totalling $11.1 million; the second, expected in 2027, is $5.8 million. The release says the dredged material goes to confined disposal facilities run by the Corps and the port authority. An earlier version of this page explained the Cleveland price by confined disposal. Since Toledo uses confined disposal too, that cannot be the whole explanation.

Mobilisation, applied to the two harbour jobs. If mobilisation did cost the illustrative $2.5 million, it would be $3.33 a yard on 750,000 cubic yards and $10.00 a yard on 250,000. That accounts for about $6.70 of the $39.73 gap between Toledo and Cleveland, about a sixth of it. On that assumption volume alone does not explain the sixfold difference either, and the awards give no breakdown that would.

The pond figures against each other. Angi gives $20 to $60 per cubic yard and $5,000 to $30,000 per acre. Pairing the low ends and the high ends, that is 250 to 500 cubic yards an acre, a layer of only about 2 to 4 inches across the whole pond (an acre one foot deep is about 1,613 cubic yards). Removing a full foot of sediment from an acre at $20 to $60 a yard would be about $32,000 to $97,000, above the per-acre range, so check which basis a quote uses. The Angi figures by size also fall per acre as ponds grow: $25,000 to $70,000 an acre for a tenth of an acre, $14,000 to $36,000 for half an acre and $15,000 to $30,000 for one acre. Mobilisation alone is quoted at $1,000 to $3,000 or more, against a whole-job figure of $2,500 to $7,000 for the smallest ponds.

The 2026 beach awards against the long-run average. $26.17 to $36.00 is about 1.5 to 2.6 times the 1970 to 2020 average of $14 to $18 in 2023 dollars shown in the table.

The federal trend in multiples. In the Congressional Research Service figures, the inflation-adjusted average rose about 3.3 times between 1970 and 2018, the dearest district was about 9.3 times the cheapest in 2014-2018, and the Rhode Island disposal fee proposal was a threefold increase.

What drives the cost

  • Disposal distance and method. Frequently the largest single factor. Placement on site, nearshore placement, offshore disposal and landfill are four completely different price levels.
  • Material type. Soft silt pumps easily. Stiff clay, compacted sand and rock each escalate the method and the cost.
  • Water depth and access. Shallow water limits dredge size. Restricted access adds mobilisation complexity.
  • Environmental windows. Fish spawning, turtle nesting and bird seasons close work windows in many locations, compressing schedules and raising cost.
  • Permitting. In the US this typically involves the Army Corps of Engineers plus state and sometimes local agencies. Timeline commonly exceeds the construction duration on small projects.
  • Debris. Sunken logs, tyres, concrete and abandoned structures stop production and are rarely in the base quote.

Getting a fair quote

Give the contractor a bathymetric survey if you have one, an estimated volume, a sediment sample result, and a clear statement of where the material can go. Those four items turn a defensive guess into a real number.

Then ask for the quote to separate mobilisation, dredging, dewatering, disposal and permitting support. A single lump sum from two contractors is not comparable, and mobilisation buried inside a per-yard rate is where most of the surprise lives.

Figures here were reviewed in November 2026 against US Army Corps of Engineers award releases and state coastal authority plans. Per-yard figures marked award-derived are arithmetic on published values and volumes, not agency-published unit rates.

FAQs

How much does dredging cost per cubic yard? A 2026 Toledo Harbor task order works out at $7.07 ($5.3 million for about 750,000 cubic yards, per a US Army release of 10 August 2026). Small pond and lake work is quoted at $20 to $60 by Angi. The other figures on this page run from $5.90 to $46.80 and were not re-traced in this update.

How much does it cost to dredge a pond? Angi gives $15,000 as the average for most residential ponds, $7,000 to $30,000 as the typical range, $20 to $60 per cubic yard and $5,000 to $30,000 per acre (undated guide, read 23 November 2026).

Why does a small job cost more per cubic yard? Fixed costs are spread over fewer yards. Angi quotes mobilisation at $1,000 to $3,000 or more for a pond job, against $2,500 to $7,000 for the whole job on the smallest ponds.

How was the Toledo figure calculated? By dividing the $5.3 million task order by the roughly 750,000 cubic yards in the US Army release. It is arithmetic on published figures, not a unit rate published by the Corps.

Related equipment cost guides

Updated 23 November 2026. Sources: US Army release on the Toledo Harbor task order (10 August 2026) and Angi pond dredging cost guide (undated), both linked above and read 23 November 2026; Congressional Research Service, Harbor Dredging: Issues and Historical Funding. Rates vary by city and season; get two or three local quotes.